This Directive shall apply to the assessment of the environmental effects of those public and private projects which are likely to have significant effects on the environment.
Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment (codification) (Text with EEA relevance)
Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment (codification) (Text with EEA relevance)
THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION,
Having regard to the Treaty on the Functioning of the European Union, and in particular Article 192(1) thereof,
Having regard to the proposal from the European Commission,
After transmission of the draft legislative act to the national parliaments,
Having regard to the opinion of the European Economic and Social Committee(1),
After consulting the Committee of the Regions,
Acting in accordance with the ordinary legislative procedure(2),
Whereas:
Council Directive 85/337/EEC of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment(3) has been substantially amended several times(4). In the interests of clarity and rationality the said Directive should be codified.
Pursuant to Article 191 of the Treaty on the Functioning of the European Union, Union policy on the environment is based on the precautionary principle and on the principles that preventive action should be taken, that environmental damage should, as a priority, be rectified at source and that the polluter should pay. Effects on the environment should be taken into account at the earliest possible stage in all the technical planning and decision-making processes.
The principles of the assessment of environmental effects should be harmonised, in particular with reference to the projects which should be subject to assessment, the main obligations of the developers and the content of the assessment. The Member States may lay down stricter rules to protect the environment.
In addition, it is necessary to achieve one of the objectives of the Union in the sphere of the protection of the environment and the quality of life.
The environmental legislation of the Union includes provisions enabling public authorities and other bodies to take decisions which may have a significant effect on the environment as well as on personal health and well-being.
General principles for the assessment of environmental effects should be laid down with a view to supplementing and coordinating development consent procedures governing public and private projects likely to have a major effect on the environment.
Development consent for public and private projects which are likely to have significant effects on the environment should be granted only after an assessment of the likely significant environmental effects of those projects has been carried out. That assessment should be conducted on the basis of the appropriate information supplied by the developer, which may be supplemented by the authorities and by the public likely to be concerned by the project in question.
Projects belonging to certain types have significant effects on the environment and those projects should, as a rule, be subject to a systematic assessment.
Projects of other types may not have significant effects on the environment in every case and those projects should be assessed where the Member States consider that they are likely to have significant effects on the environment.
Member States may set thresholds or criteria for the purpose of determining which of such projects should be subject to assessment on the basis of the significance of their environmental effects. Member States should not be required to examine projects below those thresholds or outside those criteria on a case-by-case basis.
When setting such thresholds or criteria or examining projects on a case-by-case basis, for the purpose of determining which projects should be subject to assessment on the basis of their significant environmental effects, Member States should take account of the relevant selection criteria set out in this Directive. In accordance with the subsidiarity principle, the Member States are in the best position to apply those criteria in specific instances.
For projects which are subject to assessment, a certain minimal amount of information should be supplied, concerning the project and its effects.
It is appropriate to lay down a procedure in order to enable the developer to obtain an opinion from the competent authorities on the content and extent of the information to be elaborated and supplied for the assessment. Member States, in the framework of this procedure, may require the developer to provide, inter alia, alternatives for the projects for which it intends to submit an application.
The effects of a project on the environment should be assessed in order to take account of concerns to protect human health, to contribute by means of a better environment to the quality of life, to ensure maintenance of the diversity of species and to maintain the reproductive capacity of the ecosystem as a basic resource for life.
It is desirable to lay down strengthened provisions concerning environmental impact assessment in a transboundary context to take account of developments at international level. The European Community signed the Convention on Environmental Impact Assessment in a Transboundary Context on 25 February 1991, and ratified it on 24 June 1997.
Effective public participation in the taking of decisions enables the public to express, and the decision-maker to take account of, opinions and concerns which may be relevant to those decisions, thereby increasing the accountability and transparency of the decision-making process and contributing to public awareness of environmental issues and support for the decisions taken.
Participation, including participation by associations, organisations and groups, in particular non-governmental organisations promoting environmental protection, should accordingly be fostered, including, inter alia, by promoting environmental education of the public.
The European Community signed the UN/ECE Convention on Access to Information, Public Participation in Decision-Making and Access to Justice in Environmental Matters (the Aarhus Convention) on 25 June 1998 and ratified it on 17 February 2005.
Among the objectives of the Aarhus Convention is the desire to guarantee rights of public participation in decision-making in environmental matters in order to contribute to the protection of the right to live in an environment which is adequate for personal health and well-being.
Article 6 of the Aarhus Convention provides for public participation in decisions on the specific activities listed in Annex I thereto and on activities not so listed which may have a significant effect on the environment.
Article 9(2) and (4) of the Aarhus Convention provides for access to judicial or other procedures for challenging the substantive or procedural legality of decisions, acts or omissions subject to the public participation provisions of Article 6 of that Convention.
However, this Directive should not be applied to projects the details of which are adopted by a specific act of national legislation, since the objectives of this Directive, including that of supplying information, are achieved through the legislative process.
Furthermore, it may be appropriate in exceptional cases to exempt a specific project from the assessment procedures laid down by this Directive, subject to appropriate information being supplied to the Commission and to the public concerned.
Since the objectives of this Directive cannot be sufficiently achieved by the Member States and can therefore, by reason of the scale and effects of the action, be better achieved at Union level, the Union may adopt measures in accordance with the principle of subsidiarity as set out in Article 5 of the Treaty on European Union. In accordance with the principle of proportionality, as set out in that Article, this Directive does not go beyond what is necessary in order to achieve those objectives.
This Directive should be without prejudice to the obligations of the Member States relating to the time limits for transposition into national law of the Directives set out in Annex V, Part B,
HAVE ADOPTED THIS DIRECTIVE:
Article 1
For the purposes of this Directive, the following definitions shall apply:
-
‘project’ means:
-
the execution of construction works or of other installations or schemes,
-
other interventions in the natural surroundings and landscape including those involving the extraction of mineral resources;
-
-
‘developer’ means the applicant for authorisation for a private project or the public authority which initiates a project;
-
‘development consent’ means the decision of the competent authority or authorities which entitles the developer to proceed with the project;
-
‘public’ means one or more natural or legal persons and, in accordance with national legislation or practice, their associations, organisations or groups;
-
‘public concerned’ means the public affected or likely to be affected by, or having an interest in, the environmental decision-making procedures referred to in Article 2(2). For the purposes of this definition, non-governmental organisations promoting environmental protection and meeting any requirements under national law shall be deemed to have an interest;
-
‘competent authority or authorities’ means that authority or those authorities which the Member States designate as responsible for performing the duties arising from this Directive;
-
‘environmental impact assessment’ means a process consisting of:
-
the preparation of an environmental impact assessment report by the developer, as referred to in Article 5(1) and (2);
-
the carrying out of consultations as referred to in Article 6 and, where relevant, Article 7;
-
the examination by the competent authority of the information presented in the environmental impact assessment report and any supplementary information provided, where necessary, by the developer in accordance with Article 5(3), and any relevant information received through the consultations under Articles 6 and 7;
-
the reasoned conclusion by the competent authority on the significant effects of the project on the environment, taking into account the results of the examination referred to in point (iii) and, where appropriate, its own supplementary examination; and
-
the integration of the competent authority's reasoned conclusion into any of the decisions referred to in Article 8a.
-
Member States may decide, on a case-by-case basis and if so provided under national law, not to apply this Directive to projects, or parts of projects, having defence as their sole purpose, or to projects having the response to civil emergencies as their sole purpose, if they deem that such application would have an adverse effect on those purposes.
Article 2
Member States shall adopt all measures necessary to ensure that, before development consent is given, projects likely to have significant effects on the environment by virtue, inter alia, of their nature, size or location are made subject to a requirement for development consent and an assessment with regard to their effects on the environment. Those projects are defined in Article 4.
The environmental impact assessment may be integrated into the existing procedures for development consent to projects in the Member States, or, failing this, into other procedures or into procedures to be established to comply with the aims of this Directive.
In the case of projects for which the obligation to carry out assessments of the effects on the environment arises simultaneously from this Directive and from Council Directive 92/43/EEC(5) and/or Directive 2009/147/EC of the European Parliament and the Council(6), Member States shall, where appropriate, ensure that coordinated and/or joint procedures fulfilling the requirements of that Union legislation are provided for.
In the case of projects for which the obligation to carry out assessments of the effects on the environment arises simultaneously from this Directive and Union legislation other than the Directives listed in the first subparagraph, Member States may provide for coordinated and/or joint procedures.
Under the coordinated procedure referred to in the first and second subparagraphs, Member States shall endeavour to coordinate the various individual assessments of the environmental impact of a particular project, required by the relevant Union legislation, by designating an authority for this purpose, without prejudice to any provisions to the contrary contained in other relevant Union legislation.
Under the joint procedure referred to in the first and second subparagraphs, Member States shall endeavour to provide for a single assessment of the environmental impact of a particular project required by the relevant Union legislation, without prejudice to any provisions to the contrary contained in other relevant Union legislation.
The Commission shall provide guidance regarding the setting up of any coordinated or joint procedures for projects that are simultaneously subject to assessments under this Directive and Directives 92/43/EEC, 2000/60/EC, 2009/147/EC or 2010/75/EU.
Without prejudice to Article 7, Member States may, in exceptional cases, exempt a specific project from the provisions laid down in this Directive, where the application of those provisions would result in adversely affecting the purpose of the project, provided the objectives of this Directive are met.
In that event, the Member States shall:
-
consider whether another form of assessment would be appropriate;
-
make available to the public concerned the information obtained under other forms of assessment referred to in point (a), the information relating to the decision granting exemption and the reasons for granting it;
-
inform the Commission, prior to granting consent, of the reasons justifying the exemption granted, and provide it with the information made available, where applicable, to their own nationals.
The Commission shall immediately forward the documents received to the other Member States.
The Commission shall report annually to the European Parliament and to the Council on the application of this paragraph.
Without prejudice to Article 7, in cases where a project is adopted by a specific act of national legislation, Member States may exempt that project from the provisions relating to public consultation laid down in this Directive, provided the objectives of this Directive are met.
Member States shall inform the Commission of any application of the exemption referred to in the first subparagraph every two years from 16 May 2017.
Article 3
The environmental impact assessment shall identify, describe and assess in an appropriate manner, in the light of each individual case, the direct and indirect significant effects of a project on the following factors:
-
population and human health;
-
biodiversity, with particular attention to species and habitats protected under Directive 92/43/EEC and Directive 2009/147/EC;
-
land, soil, water, air and climate;
-
material assets, cultural heritage and the landscape;
-
the interaction between the factors referred to in points (a) to (d).
The effects referred to in paragraph 1 on the factors set out therein shall include the expected effects deriving from the vulnerability of the project to risks of major accidents and/or disasters that are relevant to the project concerned.
Article 4
Subject to Article 2(4), projects listed in Annex I shall be made subject to an assessment in accordance with Articles 5 to 10.
Subject to Article 2(4), for projects listed in Annex II, Member States shall determine whether the project shall be made subject to an assessment in accordance with Articles 5 to 10. Member States shall make that determination through:
-
a case-by-case examination;
or
-
thresholds or criteria set by the Member State.
Member States may decide to apply both procedures referred to in points (a) and (b).
Where a case-by-case examination is carried out or thresholds or criteria are set for the purpose of paragraph 2, the relevant selection criteria set out in Annex III shall be taken into account. Member States may set thresholds or criteria to determine when projects need not undergo either the determination under paragraphs 4 and 5 or an environmental impact assessment, and/or thresholds or criteria to determine when projects shall in any case be made subject to an environmental impact assessment without undergoing a determination set out under paragraphs 4 and 5.
Where Member States decide to require a determination for projects listed in Annex II, the developer shall provide information on the characteristics of the project and its likely significant effects on the environment. The detailed list of information to be provided is specified in Annex IIA. The developer shall take into account, where relevant, the available results of other relevant assessments of the effects on the environment carried out pursuant to Union legislation other than this Directive. The developer may also provide a description of any features of the project and/or measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.
The competent authority shall make its determination, on the basis of the information provided by the developer in accordance with paragraph 4 taking into account, where relevant, the results of preliminary verifications or assessments of the effects on the environment carried out pursuant to Union legislation other than this Directive. The determination shall be made available to the public and:
-
where it is decided that an environmental impact assessment is required, state the main reasons for requiring such assessment with reference to the relevant criteria listed in Annex III; or
-
where it is decided that an environmental impact assessment is not required, state the main reasons for not requiring such assessment with reference to the relevant criteria listed in Annex III, and, where proposed by the developer, state any features of the project and/or measures envisaged to avoid or prevent what might otherwise have been significant adverse effects on the environment.
Member States shall ensure that the competent authority makes its determination as soon as possible and within a period of time not exceeding 90 days from the date on which the developer has submitted all the information required pursuant to paragraph 4. In exceptional cases, for instance relating to the nature, complexity, location or size of the project, the competent authority may extend that deadline to make its determination; in that event, the competent authority shall inform the developer in writing of the reasons justifying the extension and of the date when its determination is expected.