Order of the President of the Court of First Instance of 7 January 2008.
Order of the President of the Court of First Instance of 7 January 2008.
Data
- Court
- General Court
- Case date
- 7 januari 2008
Uitspraak
Order of the President of the of the Court of First Instance of 7 January 2008 – Pellegrini v Commission
(Case T-375/07 R)
Interim measures – Non-contractual liability of the Community – Commission’s failure to act – Provisional payment of damages sought in main proceedings – No prima facie case
1. Applications for interim measures – Interim measures – Conditions for granting – Prima facie case – Urgency – Cumulative nature – Balancing of all the interests involved (Arts 225 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 11-14)
2. Procedure – Application initiating proceedings – Formal requirements (Rules of Procedure of the Court of First Instance, Arts 44(1)(c) and 104(3)) (see para. 15)
Re:
| REQUEST that the Commission be ordered to pay compensation, on a provisional basis, for the financial damage allegedly suffered by the applicant because of the Commission’s failure to ensure full application and correct interpretation of the provisions of Community law governing the activities of financial intermediaries. |
Operative part
The Court:
|
1. |
Dismisses the application for interim measures; |
|
2. |
Reserves the costs. |