Judgment of the Court (Sixth Chamber) of 27 October 2011.

Judgment of the Court (Sixth Chamber) of 27 October 2011.

Data

Court
Court of Justice
Case date
27 oktober 2011

Uitspraak

Subject of the case
Operative part

Subject of the case

Re

Failure of a Member State to fulfil obligations – Infringement of Articles 8 and 11(3) of Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts (OJ 1992 L 209, p. 1) and of Articles 20 and 31(4) of Directive 2004/18/EC of the European Parliament and of the Council of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts (OJ 2004 L 134, p. 114) – Award of a contract without prior publication of a contract notice – Contract relating to additional land-registry and town-planning services – Municipalities of Vasilika, Kassandra, Egnatia and Arethousa.

Operative part

Operative part

The Court:

1. Declares that, by awarding, by means of a negotiated procedure without prior publication of a contract notice, public contracts for additional land registry and town planning services which do not appear in the initial contract concluded by the municipalities of Vasilika, Kassandra, Egnatia and Arethousa, the Hellenic Republic has failed to fulfil its obligations under Articles 8 and 11(3) of Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts, as amended by Directive 97/52/EC of the European Parliament and of the Council of 13 October 1997, and Articles 20 and 31(4) of Directive 2004/18/EC of the European Parliament and of the Council of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts;

2. Orders the Hellenic Republic to pay the costs.