Order of the General Court (First Chamber) of 15 May 2018
Order of the General Court (First Chamber) of 15 May 2018
Data
- Court
- General Court
- Case date
- 15 mei 2018
Verdict
Order of the General Court (First Chamber) of 15 May 2018 –
Commune de Fessenheim and Others v Commission
(Case T‑726/17)
"(Action for annulment - Access to documents - Letter sent by the Commission to the French authorities regarding the protocol for the compensation of the EDF Group in respect of the repeal of the permit to operate the Fessenheim Nuclear Power Plant - Implied refusal of access - Time limit for commencing proceedings - Delay - Inadmissibility)"
1. Actions for annulmentTime-limitsMandatoryExamination by the EU judicature of its own motionUndertakings made by an institutionIrrelevant
(Art. 263, sixth para., TFEU)
(see paras 20, 28)
2. Actions for annulmentActionable measuresMeaningMeasures producing binding legal effectsSilence or inaction of an institutionAssimilation to an implied decision of refusalNot includedLimitsLack of a response to a request confirming access to documents within the prescribed period
(Art. 263 TFEU; European Parliament and Council Regulation No 1049/2001, Art. 8(3))
(see paras 21, 22)
Re:
Action based on Article 263 TFEU and seeking annulment of the implied decision of 10 August 2017, by which the Commission refused to grant the applicants access to the letter sent on 22 March 2017 by the Commission to the French authorities regarding the protocol for the compensation of the Électricité de France (EDF) Group in respect of the repeal of the permit to operate the Fessenheim Nuclear Power Plant.
Operative part
1. The action is dismissed as being inadmissible.
2. There is no longer any need to adjudicate on the French Republic’s application for leave to intervene.
3. The Commune de Fessenheim, the Communauté de communes Pays Rhin-Brisach, the Conseil départemental du Haut-Rhin and the Conseil régional Grand Est Alsace Champagne-Ardenne Lorraine shall bear their own costs and those incurred by the European Commission.
4. The French Republic shall bear its own costs.