III. Legal analysis
20.
By its question for a preliminary ruling, the referring court asks the Court whether the term ‘party having a complaint’ in Article 37(11) of Directive 2009/72 must be interpreted as meaning that a final customer has the right to lodge a complaint with the national regulatory authority against the national transmission system operator, where that final customer is not directly connected to that transmission system, but is connected only to a distribution system fed by that transmission system and where the transmission of electricity is interrupted on the transmission system that feeds the distribution system to which the final customer is connected.
21.
Under Article 37(11) of Directive 2009/72, any party having a complaint against a transmission or distribution system operator in relation to that operator’s obligations under the directive may refer the complaint to the regulatory authority which, acting as dispute settlement authority, is required to issue a decision within a period of two months after receipt of the complaint.
22.
The question referred by the national court concerns the individual scope of that provision and, more specifically, the scope of the term ‘party having a complaint’ in that provision.
23.
The parties that have submitted observations to the Court, disagree on the interpretation to be given to that term. On the one hand, Crown and the European Commission propose a broad interpretation and consider that a final customer has the right to lodge a complaint against a transmission system operator even in the absence of a direct or contractual relationship between them. On the other hand, the Netherlands Government, the Finnish Government and TenneT propose a more restrictive interpretation of that term and consider that the right to lodge a complaint, provided for in Article 37(11) of Directive 2009/72, presupposes a direct relationship between the person lodging the complaint and the transmission system operator against whom the complaint is directed.
24.
In order to answer the question referred by the national court, it is therefore necessary to interpret the term ‘party having a complaint’ as defined in Article 37(11) of Directive 2009/72.
25.
As a preliminary point, I would point out that the directive does not contain a definition of either that term taken as a whole, or of the words of which it is formed, namely ‘party’ and ‘complaint’, taken individually.(5)
26.
It is the Court’s established case-law that it follows from the requirement for the uniform application of EU law and from the principle of equality that the terms of a provision of EU law which does not contain any express reference to the law of the Member States for the purpose of determining its meaning and scope, must be given an autonomous and uniform interpretation throughout the European Union, and that interpretation must take into account not only the wording of that provision but also its context and the objective pursued by the legislation in question.(6)
27.
As regards, first of all, the wording of Article 37(11) of Directive 2009/72, it should be noted that that provision uses a very broad formulation, which provides that any party having a complaint against a transmission or distribution system operator with regard to its obligations under that directive may refer the complaint to the regulatory authority.
28.
It is clear from the wording of that provision that the regulatory authority’s competence to hear a complaint is subject to two conditions: first, the complaint must be made against a transmission or distribution system operator, and second, the complaint must concern the obligations of that operator under Directive 2009/72. However, that provision does not provide that the right to lodge a complaint conferred by Directive 2009/72(7) is conditional on the existence of a direct relationship between the party intending to make a complaint and the operator against whom the complaint is made. On the contrary, the explicit use of the term ‘any’ is indicative of the broad individual scope of the provision in question.
29.
Admittedly, the use in the provision in question of the term ‘party’ may give rise to some ambiguity, in so far as that term could be interpreted as meaning that the right to make a complaint lies exclusively with persons who are parties to a contract.
30.
However, I would challenge that interpretation.
31.
First, it must be observed that, from a literal point of view, the term ‘party’ does not necessarily mean only the party to a contract, but can also be understood, in a ‘procedural’ sense, as referring to persons having an interest in referring the matter to the regulatory authority.
32.
Second, it should be noted that not all language versions of the provision in question use a word that could give rise to the abovementioned ambiguity. For example, while the English, French, Spanish and Dutch versions use a term corresponding to the Italian word ‘parte’,(8) other versions, such as, for instance, the German and Portuguese versions, use words that have no possible contractual connotation, and instead refer unambiguously to the interest of the person concerned in referring a complaint to the regulatory authority.(9) This supports an interpretation of the word ‘party’ in a sense other than ‘contractual party’. It therefore militates in favour of an interpretation of the provision in question to the effect that it does not make the possibility of lodging a complaint conditional on the existence of a contractual relationship between the person bringing the complaint and the transmission or distribution system operator against whom the complaint is lodged.
33.
Such an interpretation appears to be confirmed by the contextual analysis.
34.
To begin with, the word ‘party’ is used not only in Article 37(11) of Directive 2009/72, but also in two other paragraphs of that article, namely paragraphs 12 and 17.(10)
35.
Article 37(12) of Directive 2009/72 provides for a procedure allowing any party who is affected and who has a right to complain concerning a decision on methodologies taken pursuant to Article 37 of that directive, or, where the regulatory authority has a duty to consult, concerning the proposed tariffs or methodologies, to submit a complaint for review of the decision.(11)
36.
Article 37(17) of Directive 2009/72 provides, however, that Member States are to ensure that suitable mechanisms exist at national level under which a party affected by a decision of a regulatory authority has a right of appeal to a body independent of the parties involved and of any government.
37.
On the basis of the above analysis, neither of those provisions suggests that the term ‘party’ used in Article 37 of Directive 2009/72 – which, as mentioned in point 26 above, must be interpreted uniformly – is to be interpreted in the sense that its scope is limited only to persons who have a direct or contractual relationship with a transmission or distribution system operator.
38.
On the contrary, Directive 2009/72 specifically provides for at least one case where a person without an existing contractual relationship with the transmission or distribution system operator should be able to refer a complaint against that operator to the regulatory authority pursuant to Article 37(11) of that directive. Indeed, Article 32(2) of Directive 2009/72 provides that where a transmission or distribution system operator refuses access to the system it operates, the user concerned must be able to make use of a dispute settlement procedure in respect of that operator.
39.
In that regard, the Court clarified in its judgment of
29 October 2009,
Commission v Belgium
(C‑474/08, not published, EU:C:2009:681
), that Member States have an obligation to provide that cases in which access to the distribution or transmission network is refused may be referred to the regulatory authority by lodging a complaint in accordance with Article 37(11) of Directive 2009/72.(12)
40.
Therefore, the contextual analysis also supports an interpretation of the provision in question to the effect that the right to submit a complaint to the regulatory authority against the transmission or distribution system operator must not be made subject to the existence of a contractual relationship with that operator.
41.
Moreover, from a teleological point of view, I consider the restrictive interpretation of the term ‘party having a complaint’ within the meaning of Article 37(11) of Directive 2009/72, as proposed by the Netherlands and Finnish Governments and by TenneT, to be at odds with the purpose of Article 37(11) of Directive 2009/72 and with the role and tasks assigned by that directive to the regulatory authorities, and that it may also be inconsistent with the general aim of the directive of ensuring high levels of consumer protection.
42.
First, with regard to the purpose of Article 37(11) of Directive 2009/72, that provision seeks to enable parties affected by an action or omission on the part of a transmission or distribution system operator to refer the matter to an extrajudicial, independent and specialist body with a view to obtaining a decision that is binding on the operator, establishing and, where appropriate, ending and penalising infringements of Directive 2009/72.
43.
As the Commission has rightly pointed out, a restrictive interpretation of the term ‘party having a complaint’ as proposed by the Netherlands and Finnish Governments and by TenneT risks undermining the effectiveness of the dispute settlement mechanism provided for in Article 37(11) of Directive 2009/72. By making the possibility of lodging a complaint subject to the existence of a contractual relationship between the complainant and the transmission or distribution system operator in question, such an interpretation would have the effect of excluding from the scope of the right to lodge a complaint with the regulatory authority a significant number of users. This would affect all users who, while not having a contractual relationship with the transmission or distribution system operator, have nevertheless suffered the consequences of any infringement by that operator of its obligations under Directive 2009/72.
44.
In the same vein, I also consider that restrictive interpretation to be incompatible with the tasks and functions conferred by Directive 2009/72 on regulatory authorities, which, as can be seen from recitals 34 and 37 and from Article 37 of the directive, play a fundamental role in the overall scheme of the directive.
45.
More specifically, that interpretation undermines, in my view, the fundamental task assigned to the regulatory authorities by Article 37(1)(b) of Directive 2009/72 of ensuring that transmission and distribution system operators comply with their obligations under the directive and other provisions of relevant EU legislation.
46.
Indeed, by limiting the possibility for users to submit a complaint to the regulatory authority solely to cases where there is a direct connection to the system in question or a contractual relationship between the parties concerned would necessarily reduce the ability of the regulatory authorities to ensure compliance by transmission and distribution system operators with their obligations under Directive 2009/72. Such an approach would, in fact, limit the ability of those authorities to take cognisance of and establish any infringements by those operators of the relevant EU legislation and, therefore, the possibility of adopting binding and punitive decisions under Article 37(4)(a) and (d) of Directive 2009/72 in respect of operators who infringe that legislation.
47.
In that regard, in my view it is important to emphasise that, contrary to the arguments made by TenneT in its observations, Directive 2009/72 does not merely impose on transmission system operators functions and obligations solely in respect of users connected to their system. Indeed, it is clear from Article 12 of the directive, which specifically lists the tasks of transmission system operators, that they perform systemic functions as they are subject to obligations relating, for example, to the security of electricity supply or to the security and efficiency of the operation of interconnected systems, which far exceed the obligations arising from contractual relations with their customers connected to the transmission network. Therefore, the extent of the obligations which transmission system operators are under cannot be relied on in support of such a restrictive interpretation of the scope of the right to lodge complaints under Article 37(11) of Directive 2009/72.
48.
Second, with regard in particular to the case pending before the referring court, I would also point out that Article 37(1)(h) and (m) of Directive 2009/72 specifically assigns to the regulatory authorities the tasks, respectively, of ‘monitoring compliance with and reviewing the past performance of network security and reliability rules’ and ‘monitoring the time taken by transmission … system operators to make connections and repairs’.
49.
Third, I consider that the restrictive interpretation of the term ‘party having a complaint’ proposed by the Netherlands and Finnish Governments and by TenneT may prove to be inconsistent with the objective of Directive 2009/72 of ensuring a high level of consumer protection, which is central to the directive.(13)
50.
As is apparent from recitals 37, 42, 51 and 54 and Article 1 of Directive 2009/72, one of the principal objectives of the directive is to lay down provisions in the field of consumer protection and to establish the rights of electricity consumers by ensuring that they enjoy high levels of protection. In that regard, the Court has previously held that Article 3(7) of the directive requires the Member States to ensure a high level of consumer protection, in particular as regards dispute settlement mechanisms.(14)
51.
Accordingly, the Court has held that, where a Member State chooses to confer on the regulatory authority jurisdiction for out-of-court settlement of consumer disputes, it is clear from Article 37(11), (16) and (17) of the directive that it must be recognised that a household customer has the status of a party and the right to bring legal proceedings against the decision of the regulatory authority.(15)
52.
In the situation referred to in the preceding paragraph, in which the regulatory authority is recognised as having jurisdiction for out-of-court settlement of consumer disputes, a restrictive interpretation of Article 37(11) of Directive 2009/72 – as observed in point 43 above –would result in limiting the possibility of lodging a complaint with the regulatory authority solely to consumers who have a contractual relationship with the transmission or distribution system operator that has allegedly failed to fulfil its obligations under the directive, denying that remedy to all those consumers who, even though they do not have such a contractual relationship, nevertheless have suffered the consequences of that infringement. An interpretation that imposes that type of restriction on consumer access to the dispute settlement mechanisms provided for in Directive 2009/72 would be inconsistent with the objective, reaffirmed by the Court’s case-law, of ensuring a high level of consumer protection, particularly with regard to dispute settlement mechanisms.
53.
Similarly, such an interpretation is inconsistent with the function expressly assigned by several provisions of Directive 2009/72(16) to regulatory authorities of ensuring consumer protection and the full effectiveness of the measures laid down in the directive for that purpose.(17)
54.
In conclusion, it is apparent from the foregoing analysis that the term ‘party having a complaint’ in Article 37(11) of Directive 2009/72 must be interpreted, in my opinion, as meaning that the right to lodge a complaint against a transmission or distribution system operator provided for in that provision is not conditional on the existence of a direct or contractual relationship between the final customer wishing to make a complaint and the operator against whom the complaint is directed.
55.
In that respect, I also note that, as confirmed by the discussion which took place at the hearing, where the two conditions set out in point 28 above are met – namely that the complaint must be lodged against a transmission or distribution system operator and must concern the obligations of that operator under Directive 2009/72 – the individual reason that led the final customer to lodge the complaint is irrelevant for the purposes of the admissibility of the complaint. Specifically, there is nothing to prevent a final customer who believes that he or she has incurred loss as a result of an infringement of Directive 2009/72 by the transmission system operator from lodging a complaint against that operator before the competent regulatory authority in order to obtain evidence to be used, where appropriate, in an action for damages brought before the competent national courts.
56.
On that point, I note, incidentally, that Directive 2009/72 makes no provision for determining the evidentiary value of any decision by a regulatory authority taken pursuant to the directive in an action for damages before the civil courts. Such evidentiary value is therefore governed by the national law of each Member State. However, as the Commission observed at the hearing, those authorities have specific sectoral and technical knowledge which places them in a more advantageous position to be able to establish infringements of the obligations under Directive 2009/72. The possibility of referring a matter to those authorities by lodging a complaint therefore facilitates access to the national courts for claims for damages, which ultimately makes judicial protection against infringements of EU law more effective.