The first question
20
By its first question, the referring court asks, in essence, whether Article 16(2)(c) of Directive 2009/28 must be interpreted as meaning that priority access to the electricity grid enjoyed by electricity generating installations using renewable energy sources must be granted not only to installations producing electricity exclusively from renewable energy sources, but also to those producing from both renewable and conventional energy sources.
21
Article 16(2)(c) of Directive 2009/28 provides that Member States are to ensure that, when dispatching electricity generating installations, transmission system operators give priority to generating installations using renewable energy sources in so far as the secure operation of the national electricity system permits and based on transparent and non-discriminatory criteria.
22
Although Article 2(a) of Directive 2009/28 defines the concept of ‘energy from renewable sources’ as including, inter alia, ‘biomass’ and, in Article 2(e), the concept of ‘biomass’ as including, inter alia, ‘the biodegradable fraction of industrial and municipal waste’, it does not, however, define the scope of the concept of ‘electricity generating installation using renewable energy sources’ within the meaning of Article 16(2)(c) thereof.
23
In those circumstances, according to the settled case-law of the Court, it follows from the need for uniform application of EU law and from the principle of equality that the terms of a provision of EU law which makes no express reference to the law of the Member States for the purpose of determining its meaning and scope must normally be given an autonomous and uniform interpretation throughout the European Union; that interpretation must take into account not only its wording but also its context and the objective pursued by the legislation in question (judgment of
2 June 2022,
T.N. and N.N.(Declaration concerning the waiver of succession)
, C‑617/20, EU:C:2022:426, paragraph 35
and the case-law cited).
24
As regards, first of all, the wording of the first sentence of Article 16(2)(c) of Directive 2009/28, by referring to installations ‘using’ renewable energy sources, that wording does not, in itself, make it possible to determine whether that provision refers only to installations producing exclusively from renewable energy sources or whether it also applies to those only partly using such energy sources for that purpose.
25
Furthermore, the second sentence of that same provision, which refers to measures to be taken in order to minimise the curtailment of electricity produced from renewable energy sources, appears, given the use of the verb ‘to minimise’, to assume that priority access should also be granted to installations only partly using renewable energy sources. To not include such installations would have the effect of excluding from priority access a – potentially significant – proportion of ‘green’ electricity.
26
Next, as regards the context of which that provision forms part, Article 2(c) of Directive 2001/77 defined ‘electricity produced from renewable energy sources’ as ‘electricity produced by plants using only renewable energy sources, as well as the proportion of electricity produced from renewable energy sources in hybrid plants also using conventional energy sources’.
27
Directive 2009/28, which replaced Directive 2001/77 and was in force at the time of the facts in the main proceedings, did not reproduce that definition. In Article 2(a), that directive defines ‘energy from renewable sources’ as ‘energy from renewable non-fossil sources’ and goes on to specify which renewable sources come within that definition. Consequently, as pointed out by 50 Hertz Transmission, the classification as ‘electricity produced from renewable energy sources’ no longer depends on the type of installation in which the electricity was produced, but only on the energy sources used by those installations to produce electricity.
28
Lastly, concerning the objectives pursued by Directive 2009/28, as is apparent from Article 1 thereof, the purpose of that directive is to establish a common framework for the promotion of energy from renewable sources by setting, inter alia, mandatory national targets for the overall share of energy from renewable sources in gross final consumption of energy.
29
In addition, it is apparent from recital 60 of that directive that its aim is, through the integration of electricity from renewable energy sources into the spot market, to favour maximum use of electricity from renewable energy sources. Recital 61 of that directive states that the objective of that directive is a sustained increase in the transmission and distribution of electricity produced from renewable energy sources and that, to that end, Member States should take appropriate measures in order to allow greater penetration of electricity from renewable sources.
30
In addition, according to the Court’s case-law, the purpose of guaranteed access to the grid system provided for in Article 16(2)(b) of Directive 2009/28 is to integrate renewable energy sources into the internal market for electricity by ensuring that all electricity produced from renewable energy sources has access to the grids, allowing the use of a maximum amount of electricity produced from renewable energy sources (see, to that effect, judgment of
27 January 2022,
Fondul Proprietatea
, C‑179/20, EU:C:2022:58, paragraph 62
).
31
The objectives of maximum use of electricity produced from renewable energy sources and a sustained increase in the transmission and distribution of electricity produced from renewable energy sources would risk being undermined if an electricity generating installation not exclusively using renewable energy sources were thereby equated with an installation using only conventional energy sources and, consequently, excluded from the priority access provided for in Article 16(2)(c) of Directive 2009/28.
32
Accordingly, the answer to the first question is that Article 16(2)(c) of Directive 2009/28 must be interpreted as meaning that priority access to the electricity grid enjoyed by electricity generating installations using renewable energy sources must be granted not only to installations producing electricity exclusively from renewable energy sources, but also to those producing from both renewable and conventional energy sources.
The second to fifth questions
33
By its second to fifth questions, which it is appropriate to examine together, the referring court asks, in essence, whether Article 16(2)(c) of Directive 2009/28 must be interpreted as meaning that an installation which produces electricity from both renewable and conventional energy sources, in variable proportions, enjoys priority access to the grid solely for the share of electricity produced from renewable energy sources and, if so, what the detailed rules for applying that access priority are.
34
In the present case, the referring court asks more specifically whether an installation such as the one operated by EEW, which produces electricity from a mixture of waste containing a variable proportion of industrial and municipal biodegradable waste, enjoys priority access to the grid solely for electricity produced from that variable proportion.
35
In that regard, it should be noted at the outset that it is apparent from the definitions set out in Article 2(a) and (e) of Directive 2009/28 that, although energy obtained from the recovery of biomass constitutes energy from renewable sources, only the biodegradable fraction of, inter alia, industrial and municipal waste comes within the concept of ‘biomass’ as defined by that directive. Thus, the energy produced by thermal treatment of industrial and municipal waste is, for electricity produced from that biodegradable fraction of that waste and excluding the fraction thereof consisting of conventional waste, considered to be energy from renewable sources.
36
Next, the Court has held, in respect of Article 16(2)(b) of that directive, that although that provision refers to the possibility of establishing ‘guaranteed access’ to the grid for electricity produced from renewable energy sources, that possibility applies only to ‘green’ electricity and that provision cannot therefore serve as a legal basis for national provisions on guaranteed access for installations producing energy from a conventional source (see, to that effect, judgment of
27 January 2022,
Fondul Proprietatea
, C‑179/20, EU:C:2022:58, paragraph 65
). As observed by the Advocate General in point 46 of his Opinion, the principle of priority access to the grid referred to in Article 16(2)(c) of that directive must be interpreted to similar effect.
37
Consequently, an installation for the production of electricity using a mixture of waste of which only a variable proportion consists of industrial and municipal biodegradable waste or, more generally, using a variable proportion of both renewable and conventional energy sources, must be able to enjoy the priority access provided for in Article 16(2)(c) of Directive 2009/28, up to the sole variable proportion of electricity produced from renewable energy sources.
38
Directive 2009/28 does not, however, determine how the proportion of electricity produced from renewable energy sources by an electricity generating installation using both renewable energy sources and conventional sources must be calculated and, more specifically, whether that proportion must attain a minimum threshold in order for the electricity produced to enjoy priority access.
39
Article 16(2)(c) of that directive merely imposes two requirements.
40
In the first place, that provision makes priority of access subject to needs relating to the security of the national electricity system. In that regard, recital 60 of Directive 2009/28 states that requirements relating to the maintenance of the reliability and safety of the grid and to the dispatching may differ according to the characteristics of the national grid and its secure operation.
41
In the second place, Article 16(2)(c) of Directive 2009/28 requires that priority access be managed on the basis of transparent and non-discriminatory criteria. In that regard, recital 11 of that directive emphasises the importance of defining transparent and unambiguous rules for calculating the share of energy from renewable sources and for defining those sources. Furthermore, recital 60 of that directive reiterates, in general terms, the importance of priority access for electricity from renewable energy sources for the integration of renewable energy sources into the internal electricity market and, in particular, the point that such priority access should be reflected in national connection rules by giving connected generators of electricity from renewable energy sources the assurance that they will be able to sell and transmit electricity from renewable energy sources at all times, whenever the source becomes available.
42
It follows that the Member States have a broad discretion when they lay down the detailed rules for implementing the priority access which must be granted to electricity generating installations using renewable energy sources, provided that they comply with the objectives pursued by that directive.
43
The Court has, moreover, held previously that, by the adoption of Directive 2009/28, far from seeking to bring about exhaustive harmonisation of national support schemes for green energy production, the EU legislature based its approach on the finding that Member States apply different support schemes and on the principle that it is important to ensure the proper functioning of those schemes in order to maintain investor confidence and to enable those States to define effective national measures in order to achieve their mandatory national overall targets under the directive (judgment of
4 October 2018,
L.E.G.O
., C‑242/17, EU:C:2018:804, paragraph 53
and the case-law cited).
44
Consequently, in accordance with settled case-law, it is for the national court, which alone has jurisdiction to assess the facts and interpret the national legislation, to determine whether, in the present case, the requirements of EU law relating to the determination of the detailed arrangements for giving effect to priority access for installations using renewable energy sources are satisfied. Nevertheless, the Court, which is called on to provide answers which will be of use to the national court in the context of a reference for a preliminary ruling, may provide guidance as to the factors to be taken into account by the Member States for the purpose of applying priority access to the grid, on the basis of the documents relating to the main proceedings and the written and oral observations which have been submitted to it, in order to enable the national court to give judgment (see, by analogy, judgment of
22 September 2020,
Cali Apartments
, C‑724/18 and C‑727/18, EU:C:2020:743, paragraph 78
and the case-law cited).
45
In that regard, the requirement in Article 16(2)(c) of Directive 2009/28 to the effect that priority access to the grid must be determined on the basis of transparent and non-discriminatory criteria entails, as stated by the Advocate General in point 54 of his Opinion, that they must be clear, notified in advance by the Member States and that their application must be foreseeable for all parties concerned.
46
In addition, it is apparent from the oral argument presented at the hearing before the Court that electricity generating installations may, for the purposes of the application of Article 16(2)(c) of Directive 2009/28, be divided into three groups, comprising installations using only renewable energy sources, those using only conventional energy sources and those using a mixture of renewable and conventional energy sources, respectively.
47
It is clear, first, that, subject to the limitations relating to system security and capacity, installations in the first group must always enjoy priority access for all the electricity they produce and that the installations in the second group cannot obtain, on the basis of that provision, any priority access and, second, that the installations in those first two groups must, in principle, be treated equally within the group to which they belong.
48
As regards installations in the third group, however, it should be borne in mind, in the first place, that, as is apparent from paragraph 37 of the present judgment, priority access is granted to them only in respect of the proportion of the electricity produced from renewable energy sources. In the second place, within the third group, installations cannot be treated equally, since the proportion of renewable energy sources used by them is not necessarily the same.
49
The objective pursued by Directive 2009/28 of promoting the use of energy from renewable energy sources would risk being undermined if installations using a large proportion of renewable energy sources systematically enjoyed priority access, to the detriment of other installations which also use renewable energy sources, but to a lesser extent. The fact remains that, in the light of that same objective, the former must be able to be given priority over the latter, although without enjoying systematic priority.
50
It is therefore important that the criteria used to determine the order in which the grid operator will dispatch installations using a mixture of renewable and conventional energy sources reflect the importance of the proportion of renewable energy sources they use.
51
Similarly, it is important that those criteria take account of the special features and technical constraints which characterise the management of installations’ access to the electricity grids. In that regard, MNG Strom stated that the electricity transmission grid operator does not know, in real time, what proportion of biodegradable waste is being used by an electricity generating installation when that operator has to decide on the order in which installations are to be shut down; indeed, the operators of those installations do not know what proportion of energy is being produced from renewable sources at any given time. For its part, 50 Hertz Transmission stated that the decision on priority is an emergency measure taken in virtually a split second and that it has repercussions for downstream operators, as a result of which priority criteria must make it possible for the grid operator to be given specific guidance.
52
It should be added that the nature of electricity is such that, once it has been allowed into the transmission or distribution system, it is difficult to determine its origin and in particular the source of energy from which it was produced (judgment of
1 July 2014,
Ålands Vindkraft
, C‑573/12, EU:C:2014:2037, paragraph 87
). Similarly, when the transmission grid operator dispatches an electricity generating installation which uses both renewable and conventional energy sources, it is equally difficult to identify specifically the proportion of the electricity produced by that installation from renewable energy sources. Those technical circumstances entail a certain amount of uncertainty, with the result that it cannot be ruled out that part of the electricity declared to have been produced from renewable energy sources was not entirely so at that precise time.
53
The objective which Directive 2009/28 seeks to achieve of maximising grid access for electricity produced from renewable energy sources does not require that, at the precise time when the grid operator dispatches an electricity generating installation using an energy mix, that operator must be aware of the exact proportion of that type of electricity in the total quantity of energy supplied by that installation.
54
It is sufficient in that regard that the implementation of the criteria adopted by the competent national authorities allows, over a sufficiently long and representative period of time and in so far as technically feasible, priority access to the grid to be granted to each installation producing electricity from both renewable and conventional energy sources in proportion to the size of the share of renewable energy sources used by that installation.
55
It cannot be ruled out that the competent national authorities may, to that end, take into account a guarantee of origin within the meaning of Article 2(j) of Directive 2009/28, issued, as the case may be, to an electricity producer under Article 15 of that directive, irrespective of the fact that such a guarantee is, as is apparent from, inter alia, paragraph 1 of that provision, issued in order to enable final customers to satisfy themselves as to the exact composition of an energy supplier’s energy mix.
56
Moreover, there is nothing to prevent the competent national authorities, in the exercise of their discretion as to the setting of those criteria, from relying on certain provisions in Article 5(3) of Directive 2009/28, in particular the provision that, in multi-fuel installations using renewable and conventional energy sources, for the purposes of calculating the share of electricity produced from renewable sources, the contribution of each energy source is to be calculated on the basis of its energy content.
57
It follows from all those considerations that the answer to the second to fifth questions is that Article 16(2)(c) of Directive 2009/28 must be interpreted as meaning that an installation which produces electricity from both renewable and conventional energy sources enjoys priority access to the grid solely in respect of the proportion of electricity produced from renewable energy sources. It is for the Member States to establish the detailed rules for applying that priority access, by setting transparent and non-discriminatory criteria which, whilst taking into account requirements relating to the maintenance of reliability and safety of the grid, make it possible to establish an order of priority according to the size of the share of renewable energy sources used by each installation for the production of electricity.